How to Compare Siding Quotes in Oregon

What a siding quote should spell out, how to check a contractor's CCB license, the notices Oregon law requires at signing, and how to handle deposits.

Two siding quotes for the same Portland house can be thousands of dollars apart and both be honest. One may price new house wrap, flashing and a drainage gap behind the siding; the other may price only the boards you can see. Before comparing totals, make sure the quotes describe the same job, and that each one comes from a contractor Oregon allows to do it.

This guide covers what to check in the contractor, what a siding quote should spell out, and what Oregon law requires when you sign. Published price ranges for each kind of job are on the siding cost page.

Check the license before anything else

Every contractor who bids on residential work in Oregon must be licensed by the Construction Contractors Board (CCB). Look the business up on the CCB license search, ideally by license number. According to the CCB’s consumer tools page, the record shows:

  • whether the license is active and a surety bond is on file;
  • whether proof of liability insurance is on file;
  • whether the business is licensed for lead-based paint renovation;
  • whether it carries workers’ compensation;
  • any complaints or disciplinary actions filed with the CCB in the past 10 years.

The bond and insurance minimums depend on the license type. Under ORS 701.081, a residential general contractor carries a 25,000-dollar bond and at least 500,000 dollars of liability insurance, and a residential specialty contractor a 20,000-dollar bond and at least 300,000 dollars of insurance. Those are minimums, not a measure of quality.

The license number should be on every written bid and contract, and on the contractor’s website, under the CCB’s advertising rule (OAR 812-003-0120). A quote without one is the first thing to ask about.

The CCB also points out that Oregon does not require contractors to have construction training, which is why it recommends checking references. Ask for two or three recent siding jobs, ideally on houses like yours, and whether you can see one.

On a house built before 1978, check the lead license too

Houses painted before 1978 may carry lead paint, and Portland’s median home was built in 1966 (U.S. Census Bureau, American Community Survey 2020-2024), so most of the city’s housing is in this group. The CCB’s specialty license page is plain: only contractors licensed for Lead-Based Paint Renovation can bid or work on pre-1978 homes, once the job disturbs more than 20 square feet of painted surface outside.

Almost every siding replacement and most siding repairs cross that line. Two things to expect from a properly licensed contractor:

  • The pamphlet. Federal rules require the contractor to give you EPA’s Renovate Right pamphlet no more than 60 days before work begins (40 CFR 745.84).
  • The paperwork. The Oregon Health Authority tells lead-licensed contractors to give their client a copy of their training certificate and license.

Lead-safe setup takes time and materials, so it shows up in the price. A quote on a 1920s house with no mention of it is not a bargain; it is a different job. The same goes for asbestos on any house built before 2004: Oregon DEQ requires a survey before renovation, and the asbestos siding guide lists the lines a quote should show for it.

What a siding quote should spell out

The CCB lists what well-written construction contracts often include: a materials list, start and completion dates, a payment schedule, which permits are needed and who gets them, and written change orders signed by both parties. For siding, that translates into these lines. Hold each quote up against them.

  1. The product, by name. Brand and product line, profile (lap, panel, shingle, board-and-batten), exposure, and whether fiber cement arrives primed or factory-finished. “Hardie-type siding” is not a product.
  2. Tear-off and disposal. Whether the old siding comes off, and who hauls it away.
  3. Hidden damage, priced by the unit. Nobody knows how much rotted sheathing is behind old siding until it is off. A good quote gives a price per sheet of sheathing or per hour of framing repair, rather than a lump allowance or silence. This line matters most on hardboard and T1-11 houses.
  4. The layers behind the siding. Water-resistive barrier (house wrap), flashing at every window and door, kickout flashing where a roof edge meets a wall, and the drainage gap that Oregon’s residential code requires unless an exception applies.
  5. Trim, soffit and fascia. What is replaced, what is kept, and in what material.
  6. Paint or finish. Who paints primed boards, with what product, how many coats, and whether that is in this price or a separate contract.
  7. Permits and review. Whether any is needed, and who applies. In Portland that is usually only fire-rated walls near a property line and houses in historic or conservation districts; the Portland permits and historic rules page covers both.
  8. Lead-safe work on a pre-1978 house, as above.
  9. Schedule, cleanup and warranty. Start and finish dates, daily cleanup and magnet sweeps for nails, and what the contractor’s own workmanship warranty covers, separate from the manufacturer’s product warranty. How long siding lasts sets out what the main product warranties promise.

Why the lowest total can cost the most

Once the lines are side by side, the gaps usually explain the price difference. The common ones:

  • No hidden-damage pricing. The low bid covers the siding only, and rot found on day two becomes a change order at whatever price is set then.
  • Wrap and flashing left out. New siding over torn building paper and unflashed windows fails the way the old siding did. See water behind siding for what that looks like.
  • Paint not included. Primed fiber cement needs painting soon after it goes up; if that is a separate job, the real total is higher.
  • Allowances instead of prices. A small allowance for trim or repairs keeps the headline number low.

If two quotes still differ after that, ask each contractor to price the other’s missing lines. The answer is often more useful than the original totals.

What Oregon law requires in the contract

ORS 701.305 requires a written contract for residential work when the price is over 2,000 dollars, which covers nearly every siding job. If a smaller job grows past that figure, the contractor has five days from knowing it to put the contract in writing.

The CCB’s rule on contract contents (OAR 812-012-0110) calls for the contractor’s name, address, phone number and license number, your name and the job address, a description of the work, and the price and payment terms, along with an explanation of your rights, including the right to file a complaint with the CCB. A contract cannot take that right away (ORS 701.315).

The notices you should receive when you sign

On a residential contract over 2,000 dollars, the contractor must give you three notices on or before the day you sign, and keep proof they did (OAR 812-012-0130):

  • Consumer Protection Notice.
  • Notice of Procedure, which explains what to do if there is a dispute.
  • Information Notice to Owner About Construction Liens (ORS 87.093).

If a contractor hands you a contract without them, that says something about how the rest of the job will be run.

Deposits, payments and liens

Oregon sets no maximum deposit. What it does say is that the CCB can place a contractor on probation for taking more than half the price as a deposit and then not pursuing the work diligently, or not returning the deposit within 10 days of a demand (ORS 701.312). The CCB’s plainer advice: “Never pay the full amount up front and don’t pay in cash.”

A payment schedule tied to stages of the work (materials delivered, tear-off and repairs done, siding up, paint and cleanup finished) keeps the amount paid in line with the work done.

Liens are the other reason to watch payments. Under ORS 87.010, anyone who supplies labor or materials to the job can place a lien on the house, and the CCB warns that if a contractor does not pay subcontractors or suppliers, they may lien your property. Its advice is to verify that all bills are paid, even if you have paid the contractor in full. Asking who the siding supplier is, and whether it has been paid before the final payment, is a reasonable question.

If you change your mind

After signing, Oregon gives you until midnight of the following business day to cancel an initial residential contract in writing (ORS 701.310), unless you both agreed work would start sooner or work has substantially begun.

If the contract was signed at your home after the contractor came to you, Oregon’s home solicitation sales law gives you until midnight of the third business day (ORS 83.720). The CCB notes that this applies to remodeling and repair contracts. The federal Cooling-Off Rule gives a similar three-day right for sales of 25 dollars or more made at your home.

If part of the decision is what the work will do to the house’s value or its property taxes, see new siding, home value and Oregon taxes before comparing bids.

Questions worth asking every contractor

  • What is your CCB license number, and are you licensed for lead-based paint renovation?
  • What exactly is on the wall behind the new siding: which wrap, which flashing, and what drainage gap?
  • How do you price rotted sheathing or framing if you find it?
  • Is painting included, and with what product?
  • Who is on site: your own crew or a subcontractor?
  • What does your workmanship warranty cover, for how long, and is it in writing?
  • What is the payment schedule, and what is due before work starts?

Request a siding quote for your own house and hold it up against this list like any other bid. The siding cost page lists published price ranges to check it against.

Start My Siding Quote

No cost and no obligation. Tell us about the house and the siding problem to get started.

Questions, answered

Common questions

How many siding quotes should I get?

The Oregon Construction Contractors Board advises against agreeing to buy services on the spot and suggests getting a few more bids. Two or three written quotes built on the same scope are usually enough to see whether a price is in line, and more useful than a larger number of quotes that each describe a different job.

Can I cancel a siding contract after I sign it in Oregon?

Oregon gives the owner until midnight of the following business day to cancel an initial residential construction contract in writing (ORS 701.310), unless both sides agreed work would start sooner or work has substantially begun. If the contract was signed in your home after the contractor came to you, the home solicitation sales law allows until midnight of the third business day (ORS 83.720).

Is it normal for a siding contractor to ask for a deposit?

Yes, and Oregon law does not set a maximum. The CCB can place a contractor on probation for taking a deposit of more than 50 percent and then not doing the work diligently or not returning it within 10 days of a demand (ORS 701.312). The Board's own advice is never to pay the full amount up front and never to pay in cash.